Industrial Facility Exemption
|
 |
|
Can the ending date of a certificate be changed after it is issued by the STC?
|
|
|
|
Answer:
|
New Page 1
The statute calls for the certificate to be issued by the local unit for the
number of years it designates. The PTD staff determines the ending date by the
language in the resolution. Once the certificate is issued, the ending date
can only be changed when one of the following applies:
- STC Rule 53 which provides for an extension of time to complete the
project.
- Section 7a of the Act which applies to facilities which exceed
$150,000,000 of SEV.
- Section 16a of the Act which applies to certificates effective after
12-31-95 for which the exemption period is shorter than the maximum
allowed under section 16.
|
 |